Publication date
NEW COGENERATION PLANT: 440 kW OF THERMAL POWER
DIMARO (ITALY). BM Greenpower is building a cogeneration plant using gasification process committed by the company BI.MO. The plant is composed by four gasifiers with co-generators with a total output power of 200 kW electric and 440 thermal. The system is connected to the heating system with biomass boiler for the integration of thermal energy … Continue reading NEW COGENERATION PLANT: 440 kW OF THERMAL POWER
BM Greenpower - February 19, 2017

HPP MAGRIOLA: A 1150 kW HYDRO POWER PLANT
ITALY. BM Greenpower completed the commissiong of the Hydro Power Plant situated in Magriola, in Tuscany. The plant is equipped with a 4 jets Pelton 4 Turbine, for a 1150 kW of Mechanical Power.
BM Greenpower - February 08, 2017

ORDER FOR WOOD BIOMASS GASIFICATION PLANT
ITALY. BM Greenpower obtained a new order for the construction of a new wood biomass gasification plant, 200 Kw power, in Trentino Alto Adige. From the engineering to commissioning and performance test, BM Greenpower will supply the plant turnkey.
BM Greenpower - October 11, 2016

BM GROUP ILLUMINATES THE FAMOUS SKI RUN 3TRE
MADONNA DI CAMPIGLIO – DOLOMITES (IT). The prestigious ski run 3TRE in Madonna di Campiglio will be illuminated by BM Group, for the company MAK Costruzioni of Lavis (TN). Now it’s time to arrange the new lighting towers, 30 meters high, on which will be installed 15-18 projectors of 2000 Watt each.
BM Greenpower - June 28, 2016

FRANCIS TURBINE FOR HYDROPOWER PLANT IN TRENTO
TRENTO, ITALY. A new FRANCIS turbine is ready for shipment in the workshop of our company HYDROALP S.r.l. The turbine power of 200 kW will be installed and put into service in Trento.
BM Greenpower - October 09, 2015

SMALL HYDROELECTRIC POWER PLANT IN PRODUCTION
VERONA, ITALY: New 50 kW SHPP with Archimedean screw is now in full production. Started up a new Small Hydroelectric power plant in the surroundings of Verona, consisting of Archimedes screw, with regenerative system inverter (AFE), flow 3000 liters / second and certified CEI 0-21.
BM Greenpower - September 23, 2015

NEW AUTOMATION SYSTEM FOR HYDRO POWER PLANT
The system, developed with WinCC Scada and based on Siemens S7 plc, allows you to achieve maximum performance combined with an intuitive graphical interface. BM has also provided all the control equipment and the central power.
BM Greenpower - September 10, 2015

THE NEW WOOD PELLET HEATING PLANT HAS BEEN COMPLETED
Baselga di Piné (TN). BM Greenpower installed a new pellet heating system with the supply and installation of two boilers of 300 kW each, the loading system of the pellet and the box storage container. The connection to the existing system has been supplied by BM team.
BM Greenpower - September 08, 2015

THE NEW HPP IN VALTELLINA HAS BEEN COMPLETED
VALTELLINA: BM Greenpower completed the hydroelectric power station in “Mountain Valtellina”. BM Greenpower provided as general contractor the entire plant: turbine, generator and automation system, including the O&M services and even the works of construction.
BM Greenpower - July 17, 2015

HYDROGEN INSTALLED IN SPIAZZO (TN)
BM Greenpower consegna al comune di Spiazzo in Trentino la prima centrale HYDROGEN, soluzione micro "plug&play" che offre tempi di installazione ridotti
BM Greenpower - July 06, 2015